In 2011, water infiltration reported by school personnel and deteriorating conditions of the building envelope prompted a much needed façade and window restoration project at The Town School.
Due to school operations, however, the work schedule was limited to a 6 to 8 week time frame during summer months only. As a result, Merritt carefully planned a four-phase restoration project, designing each project phase to take place from early July through the beginning of September, over the course of four years.
PHASE I - Playground Rooftop Replacement (Summer 2011)
PHASE II - Façade Restoration (Summer 2012)
PHASE III - New Window Installation (Summer 2013)
PHASE IV - Façade Restoration of South & West Elevation (Summer 2014)
Merritt worked closely with all contactors and school personnel to ensure the safe and timely completion of work.