Name of Building: Structural Industrial Batch Plant
Country: USA
Type of Building: Tower And Trusses
Numbers of floor: In Tower Six floor + Roof
Total Tonnage: 850 Ton
Nature of the project and Software used: This was a steel detailing project. We worked on Tekla software for this project.
Hours Consumed: 3315 Hours
Turn Around time: 95 working days
Project Description: This project included working on Structural Fabrication Drawings for the following segments of the building
MIXING TOWER
EAST GANTRY
NORTH GANTRY
MAIN GANTRY
4 FURNACES
13 SILO
CULLET RETURN
SILO 11 MODIFICATION
NORTH STAIR TOWER
We had to develop the Anchor Bolt Plan, Erection Plans, Assembly Drawings, Part Drawings, Reports (Assembly List, Part List, Bolt List, etc.) and submit the.NC files to the client.
Input and Output: We received 3D model for all the phases of work as per the revision. We had to create detailed shop drawings from the input files provided.