Project Name: High School
Project Scope of Work: MEP co-ordination with Architectural Structural discipline. Develop shop drawings for all disciplines.
Size of Project: Medium Size project.
Area: 1, 12,680 sq.ft
Resources Utilized: 2 MEP Modelers.
Leadership: 1 Project Manager
Turn Around time: 20 working days
Project Description: Scope of work for this project was to work on MEP co-ordination and development of shop drawings for a high school.
Building Details: 2 storied Building
Inputs provided by client: Architecture, structure and MEP Models
Work Methodology:
Detect Clashes and resolve them through design co-ordination with Design and Engineering team.
Co-ordinate all seven trades (Architecture,structure, HVAC Electrical and Plumbing) together initially.
Generation of Shop Drawings.
Deliverables:
Clash report for the project
Co-ordinated Revit Model
Shop Drawings(2d Format)